June 2014

Final measurements and official administrative procedures

Final measurements and official administrative procedures (zaključne meritve in administrativno upravni postopki)
May 2014

Outdoor facilities: fences, outdoors equipment

Outdoor facilities: fences, outdoors equipment (zunanja ureditev: ograje, oprema)
 

May 2013

Outdoor facilities: planting greenery

Outdoor facilities: planting greenery (zunanja ureditev: zasaditev)

May 2013

Outdoor facilities: asphalts

Outdoor facilities: asphalts (zunanja ureditev: asfalti)

April 2014

Wood floors on the terraces

Wood floors on the terraces (leseni tlaki na terasah)

April 2014

Finalization of the apartments in cores A, B and C: parquet, doors

Finalization of the apartments in cores A, B and C: parquet, doors (finalizacija stanovanj v jedrih A,B in C: parket, vrata)

April 2014

Solar power plan - final works

Solar power plan on the roof - final works and set-up works (Fotovoltaična elektrarna – ina montaža in priklop)

April 2014

Solar power plan - costruction works

Solar power plant - construction and assembling works (Fotovoltaična elektrarna – Konstrukcija in groba dela)

March 2014

Railings, glass railings, canopies - Fine assembly and installation works

Railings, glass railings, canopies - Fine assembly and installation works (Ograje, steklene ograje, nadstreški – Fina montaža inštalacij)

March 2014

Corridors, staircases

Painting works: corridors, staircases (Slikopleskarska dela: hodniki, stopnišča)

March 2014

Stone flooring works in corridors and staircases

Stone flooring works in corridors and staircases (Hodniki – Kamnite obloge: hodniki, stopnišča)

March 2014

Fnalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – Elektro inštalacije: finomontaža)
March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C ((finalizacija stanovanja v jedrih A, B in C – Strojne inštalacije: finomontaža)
March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – Slikopleskarska dela: kitanje in pleskarija)
March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – Keramičarska dela: polaganje keramike v kopalnicah)

March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – zidarska dela: obzidava kopalnih kadi)
March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – Strojne inštalacije: vgradnja kopalnih kadi in tušev)

March 2014

Finalization of the apartments in cores A, B and C

Finalization of the apartments in cores A, B and C (finalizacija stanovanja v jedrih A, B in C – izvedba estrihov – finalni sloj)

March 2014

finalization of the apartments in cores A, B and C: screed implementation – styrofoam concrete

finalization of the apartments in cores A, B and C: screed implementation – styrofoam concrete (finalizacija stanovanja v jedrih A, B in C: izvedba estrihov – stirobeton)

March 2014

Finalization of the apartments in cores A, B and C: plasterboard work, bilateral closing, corner bandaging

Finalization of the apartments in cores A, B and C: plasterboard work, bilateral closing, corner bandaging (finalizacija stanovanja v jedrih A, B in C – MK dela, dvostransko zapiranje in bandažiranje stikov)

March 2014

finalization of the apartments in cores A, B and C: airtightness implementation

finalization of the apartments in cores A, B and C: airtightness implementation (finalizacija stanovanja v jedrih A, B in C: izvedba zrakotesnosti)

March 2014

Finalization of the apartments in cores A, B and C: plasterboard work, ceiling closing in the bathrooms and apartments halls

Finalization of the apartments in cores A, B and C: plasterboard work, ceiling closing in the bathrooms and apartments halls (finalizacija stanovanja v jedrih A, B in C: MK dela, zapiranje stropov v kopalnicah in hodnikih stanovanj)

March 2014

Finalization of the apartments in cores A, B and C: electrical installation- basic installation

Finalization of the apartments in cores A, B and C: electrical installation- basic installation (finalizacija stanovanja v jedrih A, B in C: elektro inštalacije: groba instalacija)

March 2014

Finalization of the apartments in cores A, B and C: mechanical installation- basic installation

Finalization of the apartments in cores A, B and C: mechanical installation- basic installation (finalizacija stanovanja v jedrih A, B in C: strojne inštalacije- groba instalacija)

February 2014

Finalization of the apartments in cores A, B and C: mechanical installation – ventilation of the apartments and bathrooms

Finalization of the apartments in cores A, B and C: mechanical installation – ventilation of the apartments and bathrooms (finalizacija stanovanja v jedrih A, B in C: strojne inštalacije: prezračevanje stanovanj in kopalnic)

February 2014

Finalization of the apartments in cores A, B and C: puttying- ceiling

Finalization of the apartments in cores A, B and C: puttying- ceiling (finalizacija stanovanja v jedrih A, B in C: kitanje stikov – stropovi)
February 2014

Finalization of the apartments in cores A, B and C: plasterboard work, unilaterally closing, preparation for installation

Finalization of the apartments in cores A, B and C: plasterboard work, unilaterally closing, preparation for installation (finalizacija stanovanja v jedrih A, B in C: MK dela, enostransko zapiranje, priprava za instalacije)

February 2014

Rendered façade: disassemble scaffolding

Rendered façade: disassemble scaffolding (kontaktne fasade: demontaža fasadnega odra)
February 2014

Rendered façade: roof

Rendered façade: roof (kontaktne fasade: streha)
February 2014

Rendered façade: sheetmetal works on the façade and edgings

Rendered façade: sheetmetal works on the façade and edgings (kontaktne fasade: kleparska dela na fasadi in obrobah)

February 2014

Rendered façade: joinery works on the façade

rendered façade: joinery works on the façade (kontaktne fasade: mizarska dela na fasadi)
February 2014

Rendered façade: shades

Rendered façade: shades (kontaktne fasade: žaluzije – zaščita pred soncem)
January 2014

Rendered façade: locksmith&blacksmith works

Rendered façade: locksmith&blacksmith works (kontaktne fasade: ključavničarska dela)

January 2014

Rendered façade: 10th and 11th floor – all façades

Rendered façade: 10th and 11th floor – all façades (kontaktne fasade: 10. in 11. nadstropje - vse fasade)

January 2014

Rendered façade: NW, NE and east façade 1st -9th floor

Rendered façade: NW, NE and east façade 1st -9th floor (kontaktne fasade: SZ, SV in vzhodna fasada 1.-9. nadstropje)

January 2014

Rendered façade: nort façade

rendered façade: nort façade (kontaktne fasade: severna fasada 1.-9. nadstropje)

January 2014

Rendered façade: south-southeast façade 1st -9th floo

Rendered façade: south-southeast façade 1st -9th floor (kontaktne fasade: južna - juogozahodna fasada 1.-9. nadstropje)
January 2014

Rendered façade: west façade logias 1st -9th floor

Rendered façade: west façade logias 1st -9th floor (kontaktne fasade: lože zahodne fasade 1.-9. nadstropje)

January 2014

Ventilated façade: south façade 5th-9th floor

Ventilated façade: south façade 5th-9th floor (prezračevana fasada: južna fasada 5.-9. nadstropje)

January 2014

Ventilated façade: west façade 1st-9th floor

Ventilated façade: west façade 1st-9th floor (prezračevana fasada: zahodna fasada 1.-9. nadstropje)

January 2014

Other installation works: elevators

Other installation works: elevators (ostala instalacijska dela: dvigala)

January 2014

Other installation works: buildings automation

Other installation works: buildings automation (ostala instalacijska dela: avtomatika objekta)
January 2014

Implementation of the basement: asphalt in basement

Implementation of the basement: asphalt in basement (izvedba kleti: tlaki v kleti)

January 2014

Implementation of the basement: electrical installation

Implementation of the basement: electrical installation (izvedba kleti: električna napeljava)
December 2013

finalization of the apartments - fences, glass fences, roofings: fine assembly

finalization of the apartments - fences, glass fences, roofings: fine assembly (finalizacija stanovanj - ograje, steklene ograje, nadstreški: fina montaža instalacij)
December 2013

Finalization of the apartments - halls: paintings works

Finalization of the apartments - halls: paintings works (finalizacija stanovanj - hodniki: slikopleskarska dela )
December 2013

PVC external carpentary: 9th floor

PVC external carpentary: 9th floor (PVC zunanje stavbno pohištvo: 9. nadstropje)
December 2013

PVC external carpentary: 8th floor

PVC external carpentary: 8th floor (PVC zunanje stavbno pohištvo: 8. nadstropje)
December 2013

PVC external carpentary: 6th floor

PVC external carpentary: 6th floor (PVC zunanje stavbno pohištvo: 6. nadstropje)
December 2013

PVC external carpentary: 4th floor

PVC external carpentary: 4th floor (PVC zunanje stavbno pohištvo: 4. nadstropje)
December 2013

Roof

Roof (streha)
December 2013

Sheetmetal works on the façade and edgings

Sheetmetal works on the façade and edgings (kleparska dela na fasadi in obrobah)

December 2013

Joinery works on the façade

Joinery works on the façade (mizarska dela na fasadi)
December 2013

Shades

Shades (žaluzije)
December 2013

Locksmith&blacksmith works

Locksmith&blacksmith works (ključavničarska dela)
December 2013

Rendered façade: 10th and 11th floor – all façades

Rendered façade: 10th and 11th floor – all façades (kontaktne fasade: 10. In 11. nadstropje vse fasade)
December 2013

Rendered façade: NW, NE and east façade 1st -9th floor

Rendered façade: NW, NE and east façade 1st -9th floor (sz, sv in vzhodna fasada 1. – 9. nadstropja)
December 2013

Rendered façade: nort façade

Rendered façade: nort façade (kontaktne fasade: severna fasada)
December 2013

Rendered façade: west façade logias 1st -9th floor

Rendered façade: west façade logias 1st -9th floor (kontaktne fasade: južna in jugovzhodna fasada 1. - 9. nadstropja)
December 2013

Rendered façade: south-southeast façade 1st -9th floor

Rendered façade: south-southeast façade 1st -9th floor (kontaktne fasade: lože zahodne fasade 1. - 9. nadstropja)
December 2013

Rendered façade: west façade logias 1st -9th floor

Rendered façade: west façade logias 1st -9th floor (kontaktne fasade: lože zahodne fasade 1. - 9. nadstropja)

December 2013

Building – finishing works: glazing of façade

Building – finishing works: glazing of façade (objekt – zaključna dela: zasteklitev fasade)

December 2013

Other installation works: elevators

Other installation works: elevators (ostala instalacijska dela: dvigala)

December 2013

Other installation works: buildings automation

Other installation works: buildings automation (ostala instalacijska dela: avtomatika objekta)
December 2013

Implementation of the basement: asphalt in basement

Implementation of the basement: asphalt in basement (izvedba kleti: tlaki)
December 2013

Implementation of the basement: electrical installation

Implementation of the basement: electrical installation (izvedba kleti: električne napeljave)

December 2013

Finishing of cores: plasters in cores

Finishing of cores: plasters in cores (sanacija jeder: ometi v jedrih)
December 2013

Finishing of cores: concreting and anchoring the slits on the stairs, cleaning and preparation for plasters

Finishing of cores: concreting and anchoring the slits on the stairs, cleaning and preparation for plasters (sanacija jeder: betoniranje in sidranje reg na stopniščnih ramah, čiščenje in priprava površin za omete)

December 2013

Plasters: 10th and 11th floor

Plasters: 10th and 11th floor (ometi: 10. In 11. nadstropje)

October 2013

Outdoor facilities - preparation and implementation of connections to the municipal infrastructure

Outdoor facilities - preparation and implementation of connections to the municipal infrastructure (zunanja ureditev - priprava in izvedba priključkov na komunalno infrastrukturo)
October 2013

PVC external carpentary: 11th floor

PVC external carpentary: 11th floor (PVC zunanje stavbno pohištvo: 11. nadstropje)
October 2013

PVC external carpentary: 10th floor

PVC external carpentary: 10th floor (PVC zunanje stavbno pohištvo: 10. nadstropje)
October 2013

PVC external carpentary: 4th floor

PVC external carpentary: 4th floor (PVC zunanje stavbno pohištvo: 4. nadstropje)
October 2013

PVC external carpentary: 3rd floor

PVC external carpentary: 3rd floor (PVC zunanje stavbno pohištvo: 3. nadstropje)

October 2013

PVC external carpentary: 2nd floor

PVC external carpentary: 2nd floor (PVC zunanje stavbno pohištvo: 2. nadstropje)

October 2013

Roof

Roof (streha)

October 2013

Sun protection shades

Sun protection shades (žaluzije – zaščita pred soncem)
October 2013

Locksmith&blacksmith works

Locksmith&blacksmith works (ključavničarska dela)
October 2013

Rendered façade: ceiling of the mezzanine

Rendered façade: ceiling of the mezzanine (kontaktne fasade: strop mezanin)

October 2013

Rendered façade: ceiling of the 1st basement

Rendered façade: ceiling of the 1st basement (kontaktne fasade: strop 1. kleti)
October 2013

Implementation of the basement: communication

Implementation of the basement: communication (izvedba kleti: komunikacija)
October 2013

Implementation of the basement: electrical installation

Implementation of the basement: electrical installation (izvedba kleti: električne napeljave)

October 2013

Implementation of the basement: ventilation

Implementation of the basement: ventilation (izvedba kleti: prezračevanje)

October 2013

Implementation of the basement: heating

Implementation of the basement: heating (izvedba kleti: ogrevanje)
October 2013

Implementation of the basement: plumbing

Implementation of the basement: plumbing (izvedba kleti: vodovodne napeljave)

October 2013

Implementation of the basement: sewage

Implementation of the basement: sewage (izvedba kleti: kanalizacija)
October 2013

Finishing of cores ABC: vertical installation: communication

Finishing of cores ABC: vertical installation: communication (instalacijske vertikale: komunikacija)
October 2013

Finishing of cores ABC: vertical installation: electrical installation

Finishing of cores ABC: vertical installation: electrical installation (instalacijske vertikale: električne napeljave)
October 2013

Finishing of cores ABC: vertical installation: ventilation

Finishing of cores ABC: vertical installation: ventilation (instalacijske vertikale: prezračevanje)

October 2013

Finishing of cores ABC: vertical installation: heating

Finishing of cores ABC: vertical installation: heating (instalacijske vertikale: ogrevanje)

October 2013

Finishing of cores ABC: vertical installation: plumbing

Finishing of cores ABC: vertical installation: plumbing (instalacijske vertikale: vodovodne napeljave)
October 2013

Finishing of cores ABC: vertical installation: sewage

Finishing of cores ABC: vertical installation: sewage (instalacijske vertikale: kanalizacija)
October 2013

Finishing of cores ABC: implementation of heat substation

Finishing of cores ABC: implementation of heat substation (sanacija jeder ABC: izvedba toplotne podpostaje)

October 2013

Finishing of cores ABC: plasters in cores

Finishing of cores ABC: plasters in cores (sanacija jeder ABC: ometi v jedrih)
October 2013

Building walls - plasters: 10th and 11th floor

Building walls - plasters: 10th and 11th floor (ometi: 10. - 11. nadstropje)
October 2013

Building walls - plasters: 5th - 9th floor

Building walls - plasters: 5th - 9th floor (ometi: 5. - 9. nadstropje)
October 2013

Building walls - plasters: ground floor and mezzanine

Building walls - plasters: ground floor and mezzanine (ometi: pritličje in mezanin)
October 2013

Building walls - plasters: 1st - 4th basement

Building walls - plasters: 1st - 4th basement (ometi: 1. - 4. klet)
October 2013

Building walls- masonry works: 10th and 11th floor

Building walls - masonry works: 10th and 11th floor (zidanje zidov: 10. - 11. nadstropje)

October 2013

Building walls- masonry works: 1st - 4th basement

Building walls - masonry works: 1st - 4th basement (zidanje zidov: 1. - 4. klet)

August 2013

Rendered façade: scaffolding works

Rendered façade: scaffolding works (kontaktne fasade: dobava in montaža fasadnega odra)
August 2013

Other installation works: communication

Other installation works: communication (ostala instalacijska dela: komunikacija)
August 2013

Vertical installation: electrical installation

Vertical installation: electrical installation (instalacijske vertikale: električne napeljave)

August 2013

Vertical installation: ventilation

Vertical installation: ventilation (instalacijske vertikale: prezračevanje)

August 2013

Vertical installation: heating

Vertical installation: heating (instalacijske vertikale: ogrevanje)

August 2013

Vertical installation: plumbing

Vertical installation: plumbing (instalacijske vertikale: vodovodne napeljave)

August 2013

Vertical installation: sewage

Vertical installation: sewage (instalacijske vertikale: kanalizacija)

August 2013

Building walls – masonry works: 5th - 9th floor

Building walls – masonry works: 5th - 9th floor (zidanje zidov: 5. - 9. nadstropje)
August 2013

Building walls – masonry works: 1st - 4th floor

Building walls – masonry works: 1st - 4th floor (zidanje zidov: 1. - 4. nadstropje)

August 2013

Building walls – masonry works: 1st - 4th basement

Building walls – masonry works: 1st - 4th basement (zidanje zidov: 1. - 4. klet)
August 2013

Slab over the 10th floor

Slab over the 10th floor (plošča nad 10. nadstropjem)

August 2013

Walls and columns in the 10th and 11th floor

Walls and columns in the 10th and 11th floor (stene in stebri 10. in 11. nadstropja)

August 2013

Slab over the 9th floor

Slab over the 9th floor (plošča nad 9. nadstropjem)

August 2013

Walls and columns in the 9th floor

Walls and columns in the 9th floor (stene in stebri 9. nadstropja)

August 2013

Slab over the 8th floor

Slab over the 8th floor (plošča nad 8. nadstropjem)

August 2013

Walls and columns in the 8th floor

Walls and columns in the 8th floor (stene in stebri 8. nadstropja)

June 2013

Rendered façade: scaffolding works

Rendered façade: scaffolding works (kontaktne fasade: dobava in montaža fasadnega odra)
June 2013

Implementation of the basement: sewage, plumbing, heating, ventilation, electrical installation

implementation of the basement: sewage, plumbing, heating, ventilation, electrical installation (Izvedba kleti: kanalizacija, vodovod, ogrevanje, prezračevanje, elektrika)

June 2013

building walls- masonry works: ground floor and mezzanine

building walls- masonry works: ground floor and mezzanine (zidanje zidov: pritličje in mezanin)

June 2013

Slab over the 4th

Slab over the 4th (plošča nad 4. nadstropjem)

June 2013

Walls and columns in the 4th floo

Walls and columns in the 4th floor (stene in stebri 4. nadstropja)
June 2013

Slab over the 3rd floor

Slab over the 3rd floor (plošča nad 3. nadstropjem)
June 2013

Walls and columns in the 3rd floor

Walls and columns in the 3rd floor (stene in stebri 3. nadstropja)

June 2013

Slab over the 2nd floor

Slab over the 2nd floor (plošča nad 2. nadstropjem)

June 2013

Walls and columns in the 2nd floor

Walls and columns in the 2nd floor (stene in stebri 2. nadstropja)

May 2013

Implementation of the basement: electrical installation

Implementation of the basement: electrical installation (izvedba kleti: električne napeljave)
May 2013

Slab over the 1st floor

Slab over the 1st floor (plošča nad 1. nadstropjem)

May 2013

Walls and columns in the 1st floor

Walls and columns in the 1st floor (stene in stebri 1. nadstropja)
May 2013

Slab over the mezzanine

Slab over the mezzanine (plošča nad mezaninom)

May 2013

Walls and columns in the mezzanine

Walls and columns in the mezzanine (stene in stebri mezanina)

May 2013

Slab over the ground floor

Slab over the ground floor (plošča nad pritličjem)

May 2013

Walls and columns in the ground floor

Walls and columns in the ground floor (stene in stebri pritličja)

February 2013

Electrical installation

Electrical installation (električne napeljave)
February 2013

Slab over the 2nd basement

Slab over the 2nd basement (plošča nad 2. kletjo)

February 2013

Walls and columns in the 2nd basement

Walls and columns in the 2nd basement (stene in stebri v 2. kleti)
February 2013

Slab over the 3rd basement

Slab over the 3rd basement (plošča nad 3. kletjo)

November 2012

Walls and columns in the 4th basement

Walls and columns in the 4th basement (stene in stebri v 4. kleti)

November 2012

Fondation slab

Fondation slab (temeljna plošča)

November 2012

Underlay concrete

Underlay concrete (podložni betoni)
April 2012

Fondation slab

Fondation slab (temeljna plošča)
April 2012

Earthworks

earthworks (zemeljska dela)
April 2012

Preparation and organization of the building site

Preparation and organization of the building site (priprava in organizacija gradbišča)

March 2011

Underlay concrete

Underlay concrete (podložni betoni)
December 2010

Construction pit

Construction pit (gradbena jama)
December 2010

Earthworks

Earthworks (zemeljska dela)
September 2010

Gas

Gas (plinska napeljava)
September 2010

Preparation and organization of the building site

Preparation and organization of the building site (priprava in organizacija gradbišča)
September 2010

Demolition works

Demolition works (rušitvena dela)

2008

Construction site before demolition works

Construction site before demolition works (situacija pred rušitvijo)